COMPLETED PROJECTS
MOSS BLUFF (DUKE ENERGY - MPH)
Egan Hub Partners, L.P. (Salt Dome Natural Gas Storage Facility)
Completed 09/2002 Evangeline, LA | Moss Bluff, TX

TKE provided Turnkey services for the removal, refurbishment, relocation, and installation of a 700 MMSCFD dehydration system including two contact towers that were converted from bubble cap trays to structured packing to accommodate cold gas dehydration. Engineering and design included foundations, piping systems, electrical control and power systems for the installation of the relocated equipment. Procurement included all equipment, valves, piping, instrumentation and controls as well as the modifications to the contact towers. Civil, Mechanical, and Electrical Construction services were provided for the removal, relocation, and installation of the equipment.

MATERIALS & SERVICES
 
  • Cavern 5 : surface piping design, withdrawal separator installation
  • Cavern 4: surface piping design